Guide prices
Small fixed unit
Opening cut, joists trimmed, upstand built, roof covering made good, plasterboard reveals ready for decoration
Medium fixed unit
As the small unit, with a larger opening up to about 1 × 2 m and additional trimming
Large or opening unit
Bigger structural work or an electric opening unit
Guide ranges for supply & fit, including structure and making good; building control or warrant fees extra. Your price is fixed in a written quote after we have seen photos or surveyed. Scaffold, access towers or a crane are priced separately if the job needs them, and building control fees, where a job needs them, are shown as their own line.
Coverage in and around Purley
Fitters travel to the job, so the address is what counts. In Purley that means postcode districts CR8, CR2 and CR5, and the same teams can just as easily take on work in Coulsdon, about 2 miles away, or South Croydon at roughly 2 miles. Survey and fitting dates are offered according to fitter availability, and travel is built into the quote rather than added later.
Buying your own, or letting us supply
Your unit or ours, the fitting standard is the same. For supply and fit we choose a new rooflight to suit the roof and price it with the installation. For fit-only we work with what you have, after confirming it arrived undamaged, that it matches the builder's opening, and that the upstand will sit at the height the maker asks for. Report any transit damage to the seller, as the product cover is theirs and the maker's. Our written guarantee applies to the fitting itself.
What we do on the day
- Insulated upstand built square, level and to the maker's height
- Roof membrane, felt or tiles made good and dressed up the upstand
- Plasterboard reveals formed inside and left ready for skim or decoration
- Warm or cold roof build-up — We find out whether the roof is insulated above or between the joists before designing the upstand.
- Upstand energy performance — We build the upstand to meet the energy limit for site-built upstands, not just to hold the rooflight up.
How a fitting day runs
Arrive and agree the plan. Sheet the floor and furniture. Set up the ladder, tower or scaffold. Check the opening, the upstand or flashing, and the unit against the paperwork. Fix and pack a new rooflight level. Seal it into the roof. Line the reveal or fit the ceiling trim. Clean the glass, clear the waste, and talk you through it. That is the shape of most fitting days, and for this type of job it usually takes two to three days.
Planning and building rules in England
In England, a new rooflight opening generally needs building regulations approval because the roof structure is altered and the glazing must meet energy rules: 2.2 W/m²K for a rooflight in an existing home, or 1.4 W/m²K (or WER Band B) for a roof window. Planning is often not needed on a house: permitted development covers rooflights that stand no more than 0.15 m proud of the roof slope and sit below the highest part of the roof. Flats, listed buildings and areas with an Article 4 direction are different, so we check your address first.
Details that speed up your quote
A fast quote needs five things: a photo of the roof from outside, one from the room below, rough sizes of the opening or the space, the roof covering (felt, single-ply, fibreglass, tiles, slate or metal), and a note on access. If you have already bought the unit, add the product link or spec sheet. And give us the postcode, CR8 or a neighbouring district.
Common questions in Purley
Can you remove and dispose of the old rooflight?
Yes. Taking out the old unit is part of any replacement job, and it leaves with the rest of the waste unless you ask to keep it. Old domes, glass and frames go through proper waste routes. If removal turns up a rotten kerb or damaged decking, we show you what we have found and agree the repair with you before going any further.
Do you make good inside after fitting?
Yes, where the quote includes it. Internal finishing usually means lining the reveal with plasterboard, taping or skimming, and fitting trim where it meets the ceiling. Some people prefer their own plasterer or decorator to finish off, which is fine. The written quote spells out exactly where our work stops, so nobody is left guessing about who does what once the unit is in.
Can you replace an old dome without redoing the whole roof?
Usually, yes. If the existing kerb is sound, level and tall enough, a new unit can often sit on it with a fresh seal to the roof covering. If the kerb is rotten or too low, we rebuild it and patch the covering around it rather than stripping the whole roof. This is checked at the survey and included in the written quote, so you know the full scope first.
Ask for a quote for your Purley roof. Survey dates are offered based on fitter availability once you are happy with the price.