Guide prices
Onto a ready upstand
Customer-supplied unit up to about 1.5 m², fitted to a prepared kerb, sealed and trimmed
With a new upstand
Insulated timber upstand built, membrane turned up and dressed, unit fitted and sealed
Large or heavy unit
Extra hands or lifting gear, larger openings, fixed or opening units
Guide ranges for labour only — you supply the rooflight. Your price is fixed in a written quote after we have seen photos or surveyed. Scaffold, access towers or a crane are priced separately if the job needs them, and building control fees, where a job needs them, are shown as their own line.
Covering NE15 and neighbouring districts
Fitters travel to the job, so the address is what counts. In Newburn that means postcode districts NE15, NE40 and NE21, and the same teams can just as easily take on work in Blaydon-on-Tyne, about 2 miles away, or Whickham at roughly 4 miles. Survey and fitting dates are offered according to fitter availability, and travel is built into the quote rather than added later.
What we check on a supplied unit
A damaged delivery is a frequent snag on fit-only work. Before the day, unpack a rooflight, photograph it, and tell the seller about any cracks or scuffs, because claims are much easier made early. We will also ask for the model or a link, so we can read the maker's instructions and check the builder's opening size and the upstand height it expects. If everything lines up, we fit it. If not, we explain what needs changing first.
What we do on the day
- Internal reveal trimmed or lined, with the protective film removed at the end
- Opening and upstand measured against the maker's drawing, timber to timber
- Check of the delivered unit, glass, fixings pack and instructions before work starts
- Access and lifting — We check how the unit gets from your drive to the roof.
- Internal versus external size — We check whether your rooflight's quoted size is the hole size or the outer frame size.
Fitting your rooflight, step by step
Where a job takes half a day to a day, the split is usually structural work first and finishing second. Early on, the fitters cut or prepare the opening, trim where needed and prepare the upstand or flashing. Then a rooflight is lifted in, fixed and made weathertight so the roof is sound before anyone moves inside. Plasterboard, trim and filler for the reveal come after. Each evening the work area is swept, and at the end the glass is cleaned and the team talks you through what was done.
Planning, building control and Newburn
England's rules in short: permitted development usually covers a rooflight on a house roof provided it doesn't stick out more than 0.15 m or rise above the ridge, though a listed building always needs consent and some streets have Article 4 directions. Building regulations apply to new openings, and replacements go through building control; as we are not registered with a competent person scheme, we use a building notice and show the fee on the quote. The energy limit for rooflights in existing homes is 2.2 W/m²K, and the 2026 Approved Document L, in force from 24 March 2027, keeps that figure.
What to send for a quick quote
What we cannot see, we have to guess, and guesses make quotes wider. So the more you send, the tighter the price. Useful: shots from the roof or garden, shots from the room underneath, a rough width and length, the roof finish, any access problems, and the product page if you have already ordered. Add the property postcode around NE15 and we will come back with a quote or a survey date.
Common questions in Newburn
Can you fit a rooflight in winter or when it is raining?
Yes, within limits. Cold is less of a problem than wet, because membranes, primers and sealants need a dry surface to bond. We plan fitting days around the forecast and may move a date if heavy rain is due. If the roof has to be opened up, it is not left overnight without a temporary weather seal, so the room below stays dry while the work is finished.
What upstand height and roof pitch does rooflight fitting need?
It depends on the product. Manufacturers usually specify a minimum upstand height above the finished roof surface, and a minimum pitch on the glass so rain runs off. We follow the maker's figures for your unit rather than a rule of thumb. If your existing kerb or roof falls short, we explain the options, such as raising the upstand or choosing a unit with built-in pitch.
Can you replace an old dome without redoing the whole roof?
Usually, yes. If the existing kerb is sound, level and tall enough, a new unit can often sit on it with a fresh seal to the roof covering. If the kerb is rotten or too low, we rebuild it and patch the covering around it rather than stripping the whole roof. This is checked at the survey and included in the written quote, so you know the full scope first.
Questions before you commit? Send them over with your Newburn postcode and we will answer them plainly, with a quote alongside.